Santa Ana Elks Lodge 794 -
Build It They Will Come!
HOFMANN  FINN   
Commercial General Contractors Building

The New Santa Ana Elks Lodge coming on Lyon Street & Edinger just off the 55 Freeway. 


The New Building is Estimated for Completion June 2019 
Click here to read the entire article: 
Below are a few renderings of our New Building and video of the construction 

 

 



























































12-5-18




















10-18-2018


















  • Structural steel detailing throughout the building. 
  • Completion of the structural steel at the Porte cohere.
  • Continued electrical rough-in.
  • Continued plumbing rough-in.
  • Continued Misc. Concrete Work
  • Continued rebar prep at pour strips.
  • Completion of exterior wall concrete curbs.
  • Completion of the framing and sheeting of the Lodge Room roof.
  • Continued framing of the upper Lodge Entry roof.
  • Continued framing and sheeting of the Service Yard roof. (The Santa Ana winds on Monday played havoc on this activity.)
  • Completion of the 2 floor steel columns, steel beams, and steel joists.
  • Continued placement of the 2 floor Verco (metal) decking. (The Santa Ana winds on Monday played havoc on this activity.)
  • Completion of the caulking and sealing of the concrete panel joints.
  • Commencement of metal stud framing on the upper roof walls. (The Santa Ana winds on Monday played havoc on this activity.)
  • Commencement of roof penetrations and head outs. (The Santa Ana winds on Monday played havoc on this activity.)
  • Commencement of the wood framing of the Porte-cochere roof.
  • Preparations for the parking lot rough excavation. (Team Ortiz, you are once again up to bat!)
9-13-18












  • This week’s activities:
The link below is this week’s aerial video of the project progress from Thursday, 09/13/18, as well as a few still photos.
 
-          Continued sacking (finishing) of the exterior of the concrete wall panels.
-          Continued erection of steel columns. 
-          Continued roof steel and bar truss installation. 
-          Continued Elks’ main entry (Lyon Street) steel erection.
-          Set structural steel head outs (Openings) for roof Air Conditioning Units
-          Continued steel deliveries.
-          Continued electrical rough-in.
-          Continued plumbing rough-in.
-          Roof drain rough-in.
-          Tilt-up Service Yard concrete panel walls
-          Misc. Concrete Work
o          Pour and finish OCCU (Tenant) elevator pit.
o          Misc. footings.
o          Rebar prep at pour strips.
o         Forming of exterior fenestrations curbs and pads
-          SCE and AT&T service trench, conduit installation and backfill along         Lyon Street from Lodge Property Line to just short of the intersection of Lyon  Street and St. Andrew’s Place.
-          Interior Concept Renderings Presentation to the Santa Ana Elks Membership.
 "Thank you Bob, Emily, Jan and Kevin, and thanks to all the members who took the time to attended!" Mike Molnar 
  • ALL THE MEMBERS OF 794, THANK YOU AND ALL YOUR STAFF MIKE FOR A JOB WELL DONE !
8-20-18










This week’s activities:
The WALLS are GOING UP! This is so amazing
Thank you Mike Molnar and all your crew.. Great Job
Thank you Bob McCalla and all our crew.. Fabulous
07-12-18












This week’s activities:
-          Completion of Layout and Forming of Concrete Wall Panels (Note that there are 41 individual concrete wall panels being cast. The largest being 40’-6” high by 31’-5 ½” wide.)
-          Continued Placement of Wall Panel Rebar.  (Note that there is approximately  128,000 lbs., or 58 tons of rebar in the panel walls.)
-          Placement of Wall Panel Imbeds and Ledgers.  (Note that there is approximately 55,116 lbs., or 25 tons of steel imbeds and ledgers in the panel walls.)
-          Completion of Placement of Metal Door Frames in Concrete Wall Panels
-          Excavate, Form, Pour and Finish On-Site Catch Basins
-          Continued Coordination with SoCal Gas for the installation of the Gas Service 
Next week’s production will feature continued wall panel installation of rebar, imbeds and ledgers in the wall panels.
07-05-18













This week’s activities:
-          Layout and Forming of Concrete Wall Panels
-          Placement of Wall Panel Rebar
-          Placement of Wall Panel Imbeds and Ledgers
-          Placement of Metal Door Frames in Concrete Wall Panels
-          Completed the excavation in installation of the Southern California Edison Primary Conduit from Main Electrical Room to Property Line
-          Completed the installation of the Pull Box and Transformer Box and Pad for Southern California Edison
-          Completed the excavation in installation of the AT&T Data/Telecommunications Primary Conduit from Main Data Room to Property Line
-          Coordination with SoCal Gas for the installation of the Gas Service 
Next week’s production will feature continued wall panel form work; and installation of rebar, imbeds and ledgers in the wall panels.
06-29-18 
Today’s progress photos of the Southern Cal Edison (SCE) transformer pad, pull box at the property line and the primary and secondary conduit installation compliments of PLE under the direction of Darren.

CLICK  The Pictures To Enlarge Them 






6-28-18
Attached are project progress photos from today.  The aerial video of the project progress as of this afternoon, Thursday, 06/28/18












  This week’s activities:
-          POS System Training (Phase 01)
-          Layout and Forming Concrete Wall Panels
-          Placement of Wall Panel Rebar
-          Placement of Wall Panel Imbeds and Ledgers
-          Placement of Metal Door Frame in Concrete Panels
-          Completed Storm Drain Installation/Tie-in
-          Completed the Bioswale on the South side of the site
-          Excavation in installation of the Southern California Edison             Primary Conduit from Main Electrical Room to Property Line
-          Installation of the Pull Box and Transformer Box and Pad               for Southern California Edison
-          Excavation in installation of the AT&T                                           Data/Telecommunications Primary Conduit 
           from Main Data Room to Property Line
-          Coordination with SoCal Gas for the installation of the Gas             Service
-          Installation of the Fire Water, Domestic Water and                         Irrigation Water Meters 
Next week’s production will feature continued wall panel form work; installation of rebar, imbeds and ledgers in the wall panels; and SCE and AT&T Primary duct bank activities.
6-21-18
Below is the link to project progress as of Friday 
SA Elks Lodge - Drone Video - 06 21 18.mp4
The activities showing are the concrete pour of the main slab and the two wall casting slabs.   Work started at 2:00 AM on Friday Morning and was completed at 6:00 PM Friday evening.  Approximately 800 yards of concrete was poured, finished and wet cut. 

  This week’s activities:
-          POS System Training (Phase 01)
-          Striping of the slab forms
-          Storm drain installation
-          Excavation of the Bioswale on the South end of the site
-          Forming of wall panels on the main slab
Next week’s production will feature continued wall panel form work, and SCE and AT&T secondary duct bank activities.
-          Slab Base
-          Main Slab Form Work
-          Slab Rebar, Imbeds, and plates
-          Depressed Slab Areas Prep.
-          Under Slab Utilities
-          POS System Set up and Training (Phase 01)
-          Water Tie-ins from the City Street to the site
-          Pad prep for the Wall Panel Casting Slabs